Project History and
Overview
|
|
|
|
|
|
|
 |
The South Village area of
Poland was identified as a potential future commercial
development area in the Town's 2005 Economic Development
Strategy and the Towns updated Comprehensive Plan. The
South Village development area includes property in the
vicinity of the intersection of Route 26 and Route 122
extending approximately 3,000 feet south and 4,000 feet
north along Route 26, west along Carpenter Road and
approximately 3,000 feet east along Route 122.
|
In 2009,
a water and sewer extension feasibility study for the South
Village area was completed by Taylor Engineering and
Community Dynamics Corporation. The study considered
various options and alignments for constructing a water and
sewer system extension from the Auburn Water and Sewerage
District systems to the South Village area. The study also
included a community outreach survey, cost-benefit analysis,
and financing analysis. The study established a total
project cost estimate of $4.3M which includes engineering,
permitting, land acquisition and construction.
|
 |
|
 |
As a
result of the recommendations from the water and sewer
extension feasibility study, a tax-increment financing (TIF)
zone was established for the South Village area by the Town
and funds were approved by citizens of Poland to construct
the utility infrastructure. The primary source of funding
for the project will be through the Maine Municipal Bond
Bank (MMBB) incorporating American Recovery and Reinvestment
Act (ARRA) funds. |
|
Water
System - The
proposed water system will include a water pump station,
storage tank and transmission mains. The pump station will
take suction from the Auburn Water District's system at a
new connection near Empire Road and boost the water to a new
water storage tank. The water storage tank will be located
on property owned by the Poland Spring resort on Ricker Hill
and will include required volume for fire fighting purposes
and peak demands. All of the water piping will be located
within the right away of Route 26 and Route 122 with the
exception of the transmission main piping from the booster
pump station to the water storage tank which will be located
on Poland Springs resort property.
Sewer
Collection System -
The
proposed sewer collection system will include gravity and
force main sewers as well as sewer lift pump stations
required to convey sewerage from the South Village area to a
terminus manhole located on the Auburn Sewer Districts
system near Empire Road. Gravity sewer is proposed along
sections of Route 26 and Route 122. Three sewer pump
stations will be required and located at the northern end of
the project along Route 26, along Route 122 near Cobble
Knoll Road and along West Crestwood Drive. Force main sewer
will be required from the Route 26 pump station to the
intersection of Route 122, from the pump station on Route
122 over Cobble Knoll and from the pump station on West
Crestwood Drive to a terminus manhole on Empire Road. All of
the sewer piping will be located within the right away of
Route 26 and Route 122. |
|
|
|